All the type of work mentioned is classed as construction work as defined by the CDM Regs 2007, which falls under part 2 of CDM i.e non notifiable, therefore as Clients you have to determine competency of the contractor before you appoint them. Appendix 4 of CDM lists key areas to look at when assessing contractors, although asking for MS and RA from previous work would help determine their competency.
Rate this!
Ged Keane
Member - 2 posts
Hi Kym
Go to the link below
http://www.hse.gov.uk/pubns/indg244.pdf
Gives you all the info you need on page 8 of the document.
Regards
Ged