More importantly, as it’s a new structure, there exists a statutory requirement - (Construction (Design and Management) - Regulation to provide such information - it’s called the Health and Safety File which is produced during the construction phase and finalised upon project completion. This document is required to be handed over to the owner / occupier of any structure / building upon completion of works and should be updated as and when additional works are undertaken on the structure / building.
So, in a nutshell, you have the law on your side. Contact the Architect and remind them of their Legal Duty to supply the information as per the afore mentioned Legislation.